  • FYI Resources (FYI) has received results from the optimised component of its recently completed high purity alumina pilot plant trial
  • The results received were well above FYI’s target of 99.99 per cent aluminium oxide, averaging 99.995 per cent aluminium oxide
  • The key function of the pilot plant is to validate and improve HPA flowsheet for technical and economic purposes
  • FYI’s share price is up a steady 11.7 per cent today with shares currently trading for 6.7 cents apiece

FYI Resources (FYI) has received results from the optimised component of its recently completed high purity alumina (HPA) pilot plant trial.

The results received were well above FYI’s target grade of 99.99 per cent aluminium oxide, averaging 99.995 per cent aluminium oxide.

Importantly, this achievement demonstrated operational improvements in the plant that will be applied to the process flowsheet and ultimately the commercial refining facility.

“We are very encouraged with the initial pilot plant operational performance and in the plant achieving above target grade of 99.99 per cent,” FYI Managing Director Roland Hill stated.

“However, we are especially pleased to now receive the excellent results from the optimised phase as it demonstrates that through the efforts of piloting, improvements and refinements to the flowsheet have been achieved,” he added.

FYI’s pilot plant trial production was designed to test the functional operation of its innovative HPA flowsheet design.

The purpose of the plant was not necessarily intended to achieve the target grade of 99.99 per cent aluminium oxide, but more so to observe and analyse the continuous end to end process operation and effectiveness of the materials handling.

Using feedstock from Cadoux, FYI completed two trial product phases.

The first phase comprised of a standard process trial while the second phase included a refined and optimised trial run which incorporated various modifications to the plant.

This resulted in obvious improvements in process efficiency and achievement in grade.

The pilot plant has played a critical role in the validation of FYI’s innovative HPA flowsheet.

It has also played an equally important role in allowing FYI and the study management team to observe actual end to end production of the flowsheet that accurately reflects the design of the full-sized commercial refinery.

During the combined phases of the pilot plant trial, FYI noted many aspects of the production materials handling where refinements and improvements could be incorporated to the flowsheet design.

These combined design and operational improvements may have a positive impact to the overall quality of HPA that will be produced but also in FYI’s ability to achieve a more reliable and consistent high grade.

FYI’s share price is up a steady 11.7 per cent today with shares trading for 6.7 cents apiece at 1:10 pm AEDT.

FYI by the numbers
More From The Market Online

AML3D secures Australian defence government contract

AML3D signed a contract with the Australian Government Defence Science and Technology Group (DSTG) to supply…

Purifloh makes progress on destroying PFAS ‘forever chemicals’

PFAS substances are sometimes called "forever chemicals," for they don't break down naturally in the environment.…

SRG Global secures $150m in new contracts across Australia

SRG Global (ASX:SRG) reaffirmed its strong presence in the Australian market by acquiring multiple contracts for…

HighCom inks fresh body armour order worth $4.7M

HighCom – formerly known as XTEK – has announced its receipt of a contract order for…