  • Montem Resources’ (MR1) Tent Mountain re-start project is delayed after the Canadian Government calls for a Federal Impact Assessment
  • The coal mine will now undergo a five-stage process that includes input from a range of government, public and indigenous groups
  • It is unknown how much of a delay it will bring to the restart of the project, which was scheduled to produce the first coal in 2023
  • On market close for the day, Montem is in the grey and trading at 3 cents per share

Re-start at Montem Resources’ (MR1) Tent Mountain project has been delayed while the project undergoes a Federal Impact Assessment.

The assessment has been ordered from the Canadian Government under the Impact Assessment Act.

Tent Mountain is a coal mine that is located in the Crowsnest Pass, and straddles both sides of the southwest Alberta and southeast British Columbia border.

The mine will now undergo a five-stage process that includes input from a range of government, public and indigenous groups.

Montem expects the assessment to be a timely and effective process and is likely to delay permitting for the project, which is scheduled to produce first coal in 2023.

It is unknown how much of a delay the assessment will cause to the project.

Notably, Environment Canada has previously visited the site twice and confirmed that it did not meet threshold limits that would trigger a Federal Impact Assessment.

“We note Minister Wilkinson’s decision to designate the Tent Mountain Mine Re-start Project to undergo a Federal Impact Assessment. This means we now have clarity on the regulatory pathway required to re-start the mine, although this will likely result in a delay to the planned start date of 2023,” CEO Peter Doyle said.

“Throughout 2020 and 2021 we have been preparing the Environmental Impact Assessment (EIA) and are on course to lodge the EIA with the provincial regulator later this year. We remain confident we are designing and presenting a project at Tent Mountain that minimizes the impact on local environment.”

On market close for the day, Montem is in the grey and trading at 3 cents per share.

MR1 by the numbers
More From The Market Herald

" Siren Gold (ASX:SNG) to begin Reefton scoping study

Siren Gold (SNG) has contracted GR Engineering Services (GRES) to complete a scoping study for its Reefton gold project in New Zealand’s South

" Paterson Resources (ASX:PSL) completes diamond drilling at Grace project

Paterson Resources (PSL) has noted the potential of an underlying mineralised system at its Grace copper-gold project in Western Australia.
Critical Resources (ASX:CRR) - Chairman, Robert Martin

" Critical Resources (ASX:CRR) engages contractor for Mavis Lake airborne survey

Critical Resources (CRR) has engaged a contractor to undertake an airborne electromagnetic survey at the Mavis Lake Lithium Project.
Aeris Resources (ASX:AIS) - Executive Chairman, André Labuschagne

" Aeris Resources (ASX:AIS) shares fall following soft quarterly production figures

Junior miner Aeris Resources (AIS) tumbled on the ASX today after the company’s latest quarterly report revealed soft quarter-on-quarter copper and gold production.