King River Resources (ASX:KRR) - Chairman, Anthony Barton
Chairman, Anthony Barton
Source: Business News
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • King River Resources (KRR) is progressing the pre-feasibility study (PFS) for the production of high-purity alumina (HPA) from its Speewah project in WA
  • KRR has improved the refinement process with indications it could produce alpha-alumina – the highest-grade product
  • A mining study and marketing and environmental reports have also been completed
  • The company now needs to produce larger samples for independent testing to prove the product’s purity
  • Once plant and infrastructure design and costings are finalised, KRR will expedite the release of the PFS as soon as possible
  • King River Resources closed Wednesday’s session 10.4 per cent lower at 4.3 cents per share

King River Resources (KRR) is progressing the pre-feasibility study (PFS) for the production of high-purity alumina (HPA) from its Speewah project in WA.

While there are still several milestones to be achieved, the company has made firm progress since its last update in mid-May.

Refine-tuned

The production of premium-grade HPA is no mean feat. KRR first reported its achievement of 99.99 per cent-pure product in April, but needed to do further work to refine and streamline its processes.

The company has now ticked several boxes in fine-tuning production.

Aside from isolating contaminants in certain reagents and from some equipment, KRR has delivered stage two purification recovery of 81.5 per cent – surpassing the 80 per cent PFS target.

Even more importantly, refinements to the purification process indicate the company should be able to produce not just HPA, but alpha-alumina – the highest grade product.

This process refinement work, alongside a completed mining studies and marketing and environmental reports, show King River is progressing well towards the final PFS.

Next steps

King River must now prove its processes before it can finalise the PFS.

The company must repeat the 99.99 per cent HPA delivered in April, but in a larger sample to be submitted for verification analysis.

This must be verified by independent testers, while samples will also undergo X-ray diffraction analysis to confirm the HPA is 100 per cent alpha-alumina.

The company has also contracted Como Engineers to deliver the plant and infrastructure design and costings. These reports are nearing completion, and are just waiting on final model validation and review.

Pending the above steps, the company will release the Speewah PFS as soon as possible.

King River Resources closed Wednesday’s session 10.4 per cent lower at 4.3 cents per share.

KRR by the numbers
More From The Market Online

Winter drilling yields thick lithium for Loyal in Canada

Loyal Lithium has picked up multiple high-grade results close to the surface from three known spodumene…

High grade sniffs in Africa push Mako shares up 14%

Mako Gold Ltd (ASX: MKG) has seen its shares jump above 14 percent on news that it has discovered a high grade zone

Chariot ends quarter charged up on lithium find in Wyoming

Chariot Corporation has confirmed high grade spodumene at its flagship play Black Mountain in the USA…

BHP confirms £31.1B takeover bid for Anglo American

BHP HAS confirmed its offer to takeover fellow mining giant Anglo American plc, following press speculation…